Public Works -Road Work for 2024-2025

Update on road work as of 5/28/2024.

This list will be updated as the season goes on, please check back for updates.

Thurrell Road- Blasting and crushing completed. Waiting on power and utility lines.

Hooper Sands Road- Erosion area. June 3rd. 2 weeks to complete.

Black Swan Drive- On paving schedule.

Belle Marsh Bridge- New deck. June 17th. Will take 2 weeks to complete.

Boyd's Corner Road-

Willow Drive-